Designer
uses the principles of hydraulics to size all the components in the system and
to ensure adequate flow and pressure to properly operate all the sprinklers on
the project.
Each
circuit has four, medium-sized rotor pop-up sprinklers that throw 47 ft (14,33 m) at 55 psi (3,8 bar), and each require 9.8 gpm (2,22 m3/h or 0,62 L/s). The designer has spaced them in an equilateral
triangular pattern at 50% spacing, but has chosen a different lateral pipe
configuration for each circuit. For reference, the various pipe sections of
each lateral have an identification letter.
The
designer knows that the water supply must reach even the furthest sprinkler out
on the line with a minimum of 55 psi (3,8 bar) to get the desired performance
at the selected spacing.
The
route this sizing procedure follows along the various pipes in the circuit is
called the critical circuit length. This route is defined as the longest path
in the circuit that the water will have to travel. The critical length may also
be described as the length between the valve and the most distal
sprinkler.
Looking at Circuit #1 in the example, it’s easy to see that the critical
circuit length for this lateral includes all the pipe sections, section “A”
through section “D.” The longest path from the valve to the most distal
sprinkler is through all the lateral pipes.
In Circuit #2, the designer has split the lateral with the valve in the center
of the circuit. The circuit is not split exactly in half. If it was, the
designer could use either side of the circuit as the critical path. There is a
slightly longer water path from the valve down through sections “C” and “D” to
the furthest sprinkler. Sections “C” and “D,” therefore, make up the critical
circuit length for example two. With the type of pipe selected and the critical
lengths determined, the designer is ready to use the Class 200 PVC pipe chart
and the 5 ft/s (1,5 m/s) method to size the lateral lines.
One
of the advantages of splitting a sprinkler circuit is clearly evident in the
above example. By splitting Circuit #2 and feeding it from a centrally located
valve position, the designer has eliminated the need for the two larger pipe
sizes. In addition to saving the cost of these bigger pipes, the cost of the
larger fittings is gone and, if all the circuits of this size were similar, the
contractor could standardize the materials inventory for the project. The
circuit is also balanced with less pressure variation between sprinklers.